Solved

What Are CCC's Estimated Remaining Construction Costs on the Project

Question 64

Multiple Choice

What are CCC's estimated remaining construction costs on the project at the end of 2009?


A) $90 million
B) $135 million
C) $225 million
D) None of these is correct Percentage completion to date = 60 % = Actual costs to date of $135 million / Total estimated project costs of $X.Solve for X.Estimated total costs = $225 million; therefore, Estimated remaining costs of construction = $225 million $135 million = $90 million.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents