What are CCC's estimated remaining construction costs on the project at the end of 2009?
A) $90 million
B) $135 million
C) $225 million
D) None of these is correct Percentage completion to date = 60 % = Actual costs to date of $135 million / Total estimated project costs of $X.Solve for X.Estimated total costs = $225 million; therefore, Estimated remaining costs of construction = $225 million $135 million = $90 million.
Correct Answer:
Verified
Q59: In its 2009 year-end balance sheet, Reliable
Q60: In 2009, JRE2 would report (rounded to
Q61: Assume that Steffi signed a $50,000 installment
Q62: What is the fixed contract price for
Q63: Assume that Steffi paid the $50,000 in
Q65: Assuming BCC uses the percentage-of-completion method of
Q66: What were the construction billings by CCC
Q67: In 2010, Indiana incurred costs of $58.5
Q68: Assume that Steffi signed a $50,000 installment
Q69: Assume that at the time of signing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents