What is the fixed contract price for CCC's project?
A) $120 million
B) $225 million
C) $345 million
D) None of these is correct Gross profit recognized in 2009 of $72 million = 60% of estimated gross project on the project.Therefore, total gross profit is estimated at $72 million/.6 = $120 million.Since Gross profit = Contract price Estimated total construction costs of $225 million, the Contract price = $120 million + $225 million = $345 million.
Correct Answer:
Verified
Q57: In 2008, Lake would recognize realized gross
Q58: In 2008, JRE2 would report (rounded to
Q59: In its 2009 year-end balance sheet, Reliable
Q60: In 2009, JRE2 would report (rounded to
Q61: Assume that Steffi signed a $50,000 installment
Q63: Assume that Steffi paid the $50,000 in
Q64: What are CCC's estimated remaining construction costs
Q65: Assuming BCC uses the percentage-of-completion method of
Q66: What were the construction billings by CCC
Q67: In 2010, Indiana incurred costs of $58.5
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents