Jean is managing a project in his organization. The planned value for this project is $4,500. At the end of eight weeks, he finds that his earned value is $3,500. What is the present schedule variance for the project? What does the variance signify?
A) $-1,000; behind schedule
B) $+1,000; ahead of schedule
C) $-1,000; on schedule
D) $+1,000; on schedule
E) $+1,000; behind schedule
Correct Answer:
Verified
Q55: Cost variance CV) is _.
A) earned value
Q56: _ is the estimate of the amount
Q57: What are parameters and parametric estimates?
Q58: _ is a method of comparing the
Q59: Which is the most accurate and time-consuming
Q61: The ratio of the earned value to
Q62: During the project, the manager can evaluate
Q63: The RFP is sent to a list
Q64: Estimates that are calculated by multiplying measured
Q65: The term _ refers to the budgeted
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents