_____ is the estimate of the amount of money needed to fill the unfinished part of the project.
A) Budget at completion
B) Estimate to complete
C) Schedule Performance Index
D) Cost Performance Index
E) Budgeted cost of work performed
Correct Answer:
Verified
Q51: _ is the sum of money spent
Q52: _ is the sum of budgeted expenses
Q53: A positive cost variance CV) indicates that
Q54: Compare and contrast contingency reserves and management
Q55: Cost variance CV) is _.
A) earned value
Q57: What are parameters and parametric estimates?
Q58: _ is a method of comparing the
Q59: Which is the most accurate and time-consuming
Q60: Jean is managing a project in his
Q61: The ratio of the earned value to