Given W = D * U for an effort-driven task.Assume an 8-hour workday.Initially,task R was assigned to Bob.Bob was expected to accomplish 32 hours of work in five days.If Bob were 100 percent available to work on task R during the entire five days,his efficiency rate is __________%.
A) 80
B) 70
C) 60
D) 75
Correct Answer:
Verified
Q8: _ describes the amounts of individual resources
Q9: _ times result from an attempt to
Q13: The use of _ activity time estimates
Q23: Using Goldratt's meaning of the word "dependent,"
Q39: _ refers to the amount of time
Q43: List some of the common priority rules
Q44: When doing multiproject scheduling,each individual project is
Q46: Discuss some other causes of the strong
Q50: Suggest some options for leveling the load
Q51: _ are tasks that logically follow a