When doing multiproject scheduling,each individual project is represented by a network of tasks.We can form a single network of these projects by connecting them with dummy activities and / or ___________.
A) pseudo activities
B) small tasks
C) pseudonyms
D) subnetworks
Correct Answer:
Verified