Question 21
Multiple Choice
Monitoring contract performance and making changes or taking corrective actions when needed refers to which of the following Project Procurement Management processes?
Question 22
Multiple Choice
Managing the relationship and contract between the buyer and seller is part of _____.
Question 23
Multiple Choice
Under this type of contract,the buyer pays the seller for the time and materials required to complete the work and the unit rates are set.
Question 24
Multiple Choice
A type of contract where the fixed price is negotiated or set as the final price for a specific product or service describes a:
Question 25
Multiple Choice
A contract…
Question 26
Multiple Choice
Negotiating,selecting,and contracting with a seller for a particular product of service refers to which of the following Project Procurement Management processes?
Question 27
Multiple Choice
Obtaining bids,quotes,proposals,literature,and other information from potential sellers or service providers refers to which of the following Project Procurement Management processes?
Question 28
Multiple Choice
Completing and settling each contract after any open items or settlements are resolved refers to which of the following Project Procurement Management processes?
Question 29
Multiple Choice
Determining whether the contract needs to be amended refers to which of the following Project Procurement Management processes?
Question 30
Multiple Choice
A _____ is when a consulting firm develops an application for a client at a negotiated price.
Question 31
Multiple Choice
Making decisions as to what will be purchased or acquired as well as determining the logistics of when purchases will be made and how refers to which of the following Project Procurement Management processes?