Budget At Completion BAC is __________
A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of the above
Correct Answer:
Verified
Q21: Schedule Variance (SV) is _
A) how much
Q28: In Project Communications Management,_focuses on the collection
Q29: In Project Communications Management,identifying people or organizations
Q32: Actual Cost AC is _
A)how much we
Q36: EV-AC =
A)Cost performance index CPI)
B)Scheduled performance index
Q36: Barring a change in project scope and
Q37: In Project Communications Management,providing relevant and timely
Q39: If we know the Actual Cost of
Q40: Estimate at Completion (EAC) is _
A) how
Q56: A _ describes the present state of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents