It is normal for activities on the critical path to be delayed without delaying the entire project.
Correct Answer:
Verified
Q11: The final activity's earliest finish time is
Q12: The earliest start time for an activity
Q13: Precedence relationships among activities are critical in
Q14: Shortening activity times,which is usually accomplished by
Q15: It is possible to have more than
Q17: The latest finish time for an activity
Q18: A path through a project network must
Q19: A critical activity can be part of
Q20: The length of time an activity can
Q21: Arcs in a project network indicate
A)completion times.
B)precedence