The final activity's earliest finish time is the anticipated project duration.
Correct Answer:
Verified
Q6: PERT and CPM are applicable only when
Q7: Constraints in the LP models for crashing
Q8: When activity times are uncertain,total project time
Q9: When activity times are uncertain,an activity's most
Q10: A key distinction of the critical path
Q12: The earliest start time for an activity
Q13: Precedence relationships among activities are critical in
Q14: Shortening activity times,which is usually accomplished by
Q15: It is possible to have more than
Q16: It is normal for activities on the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents