When activity times are uncertain,total project time is normally distributed by considering the overall mean being equal to the sum of the means of all of the critical activities.
Correct Answer:
Verified
Q3: The project manager should monitor the progress
Q4: The normal distribution tends to be a
Q5: The earliest start time for an activity
Q6: PERT and CPM are applicable only when
Q7: Constraints in the LP models for crashing
Q9: When activity times are uncertain,an activity's most
Q10: A key distinction of the critical path
Q11: The final activity's earliest finish time is
Q12: The earliest start time for an activity
Q13: Precedence relationships among activities are critical in