Solved

Mya Is Managing a Project

Question 58

Multiple Choice

Mya is managing a project.Unfortunately,the entire project team lost four days due to a hurricane in the area and a couple of the project team lost even more time when dealing with insurance claims and rebuilding.At the six-week mark of a nine-week project,she figures the team is one week behind.What might be the BEST solution?


A) Add several people to the project to get it back to schedule
B) Do not change the schedule, but expect the project and development teams to work longer days and every-other weekend.
C) Since the project is about 16% behind, increase the project to about 10-and-one-half weeks
D) Since the project is about 20% behind, increase the project to about 12 week.
E) Add three people to the project - AND - increase the overall project by one week (to a total of ten weeks)

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents