Rich Is a Manager in the Accounting Department

Question 60

Multiple Choice

Rich is a manager in the accounting department.After the system proposal is approved,he realizes that he did not mention that they want the new system to run on laptops,mobile PDA's and other mobile devices with a secure login and all data should be encrypted to meet the latest security guidelines.He wants to make sure this is included in the project.This probably is:


A) Scope creep
B) Technical feasibility
C) Infrastructure requirement
D) Already included in the system proposal
E) Unrelated to the project