Solved

After the SOP Process Has Generated the Production Plan

Question 55

Multiple Choice

After the SOP process has generated the production plan,


A) SOP executes the plan.
B) The plan is conveyed to MRP for execution.
C) The plan is transferred to demand management.
D) SOP uses the plan to generate execution plan.
E) The plan is saved as a production version.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents