In a CPM/PERT network the critical path is the
A) lowest path through the network.
B) highest path through the network.
C) shortest path through the network.
D) longest path through the network.
Correct Answer:
Verified
Q84: The LS and LF are calculated using
Q85: Consider the following project.
Q86: The advantage of a Gantt chart over
Q87: On an AOA diagram, a _ represents
Q88: The activities that must be completed prior
Q90: Project control involves
A) crashing.
B) three time estimates.
C)
Q91: Consider the following project.
Q92: If t is the expected completion time
Q93: A GANTT chart represents mainly
A) an immediate
Q94: Consider the following project.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents