A GANTT chart represents mainly
A) an immediate identification of predecessor task.
B) a record-keeping device used in scheduling activities.
C) a general identifier.
D) the number of workers directly involved in the project.
Correct Answer:
Verified
Q88: The activities that must be completed prior
Q89: In a CPM/PERT network the critical path
Q90: Project control involves
A) crashing.
B) three time estimates.
C)
Q91: Consider the following project.
Q92: If t is the expected completion time
Q94: Consider the following project.
Q95: Consider the following project.
Q96: A list of the tasks, broken down
Q97: The critical path is the _ path
Q98: On an AOA diagram, a _ represents