A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
A) 7/9
B) 7/6
C) 1/3
D) 2/3
Correct Answer:
Verified
Q106: A PERT/CPM activity has an optimistic time
Q107: Which of these statements regarding project crashing
Q108: Consider the following project.
Q109: The normal cost for an activity is
Q110: The diagram below shows the activities
Q111: A PERT/CPM activity has an optimistic time
Q113: Consider the following project.
Q114: Joe used a project management software package
Q115: Consider the following project.
Q116: Consider the following project.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents