Solved

The Diagram Below Shows the Activities on the Nodes, and the Table

Question 110

Multiple Choice

The diagram below shows the activities on the nodes, and the table shows the normal time and crash time (in days) and cost for each activity.
 The diagram below shows the activities on the nodes, and the table shows the normal time and crash time (in days)  and cost for each activity.       \begin{array} { | c | c | c | c | }  \hline \text { Activity } & \text { Normal Time } & \text { Crash Time } & \begin{array} { c }  \text { Cost per day } \\ \text { to crash } \end{array} \\ \hline \text { A } & 6 & 6 & - - - \\ \hline \text { B } & 10 & 8 & \$ 100 \\ \hline \text { C } & 5 & 4 & \$ 300 \\ \hline \text { D } & 4 & 1 & \$ 700 \\ \hline \text { E } & 9 & 7 & \$ 500 \\ \hline \text { F } & 2 & 1 & \$ 650 \\ \hline \end{array}  -Which activity should be crashed to reduce the project completion time by one day? A)  B B)  C C)  D D)  E
 Activity  Normal Time  Crash Time  Cost per day  to crash  A 66 B 108$100 C 54$300 D 41$700 E 97$500 F 21$650\begin{array} { | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Crash Time } & \begin{array} { c } \text { Cost per day } \\\text { to crash }\end{array} \\\hline \text { A } & 6 & 6 & - - - \\\hline \text { B } & 10 & 8 & \$ 100 \\\hline \text { C } & 5 & 4 & \$ 300 \\\hline \text { D } & 4 & 1 & \$ 700 \\\hline \text { E } & 9 & 7 & \$ 500 \\\hline \text { F } & 2 & 1 & \$ 650 \\\hline\end{array}
-Which activity should be crashed to reduce the project completion time by one day?


A) B
B) C
C) D
D) E

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents