Develop a solution for the following line balancing problem,allowing a cycle time of 5 minutes.
a.Draw the precedence diagram for the set of tasks.
b.Calculate the theoretical minimum number of workstations.
c.Balance this line using the longest task time heuristic.
d.What tasks are assigned to which stations?
e.Does the solution have the minimum number of stations? Explain.
f.How much idle time is there,summed over all workstations?
g.What is the efficiency of this line?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q122: Four hundred and eighty minutes of production
Q126: Cyclone Appliances has developed a new European-style
Q129: A firm operates a flow shop building
Q132: An assembly line consists of 21 tasks
Q286: Which of the following is a common
Q301: Explain what the purpose of assembly-line balancing
Q307: Assembly line balancing has just been used
Q308: _ is the maximum time that the
Q310: Identify the five common layout heuristics used
Q315: Identify the formulas for the following terms
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents