Cyclone Appliances has developed a new European-style convection oven that will be made on an assembly line.The schedule requires 80 ovens in an 8-hour day.The assembly includes seven tasks.The table below indicates the performance time and the sequence requirements for each task.
(a)What is the cycle time for this assembly operation?
(b)What is the theoretical minimum number of workstations?
(c)Draw the precedence diagram.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q122: An electronics manufacturer makes remote control devices
Q123: An assembly line has been designed to
Q124: You have been asked to balance a
Q129: A firm operates a flow shop building
Q130: Develop a solution for the following line
Q132: An assembly line consists of 21 tasks
Q286: Which of the following is a common
Q308: _ is the maximum time that the
Q310: Identify the five common layout heuristics used
Q317: A(n) _ line is a machine-paced product-oriented
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents