You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units per eight-hour day.Task times and precedence relationships are shown in the table below.
a.Draw the precedence diagram.
b.Determine the desired cycle time.
c.Determine the theoretical minimum number of stations needed.
d.Balance this line using the most following tasks heuristic.
e.What is the efficiency of the line obtained in part d?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q107: A production line is to be designed
Q122: An electronics manufacturer makes remote control devices
Q123: An assembly line has been designed to
Q126: Cyclone Appliances has developed a new European-style
Q129: A firm operates a flow shop building
Q132: An assembly line consists of 21 tasks
Q282: In a product-oriented layout, what is the
Q286: Which of the following is a common
Q310: Identify the five common layout heuristics used
Q317: A(n) _ line is a machine-paced product-oriented
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents