An electronics manufacturer makes remote control devices for interactive-cable-TV systems.The following assembly tasks must be performed on each device.
a.Draw the precedence diagram for this problem.
b.What is the sum of the task times?
c.What cycle time will allow the production of 200 units over a ten-hour day?
d.What is the theoretical number of workstations needed?
e.Balance this assembly line using the heuristic most following tasks and the heuristic longest operation time.
f.How do these two solutions differ? Which do you prefer; why?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q102: The assumptions necessary for a successful product-oriented
Q107: A production line is to be designed
Q123: An assembly line has been designed to
Q124: You have been asked to balance a
Q126: Cyclone Appliances has developed a new European-style
Q132: An assembly line consists of 21 tasks
Q282: In a product-oriented layout, what is the
Q286: Which of the following is a common
Q299: Which of the following is one of
Q317: A(n) _ line is a machine-paced product-oriented
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents