A facility is trying to set up an assembly line,and has identified the various tasks,and their relationship to each other,as shown in the following table.Managers wish to produce 600 units per day,working two 8-hour shifts.
(a)Draw a network diagram of precedence relationships.
(b)Compute the required cycle time per unit in seconds.
(c)Compute the minimum number of workstations required to produce 600 units per day.
(d)Balance this line using the longest processing time heuristic.
(e)What is the efficiency of the line obtained in part (d)?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q135: An assembly line consists of 158 tasks
Q136: A company is designing a product layout
Q141: Hemo-tech,Inc.,a biomedical technology and research laboratory,produces a
Q143: An assembly line with 11 tasks is
Q145: An assembly line is assigned as follows.Station
Q146: A firm is planning to set up
Q283: If a layout problem is solved by
Q296: Which of the following is NOT a
Q311: A company is trying to balance production
Q319: What are the advantages and disadvantages of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents