Question 41
Essay
An order has been placed for 50 units of Product A and 60 units of Product B.There are currently 35 units of Product B on hand.Each A requires 2 units of Part C; each B requires 5 units of C.There are 160 units of C available. (a)Calculate the net requirements for B. (b)Calculate the gross requirements for C. (c)Calculate the net requirements for C.
Question 42
Essay
Explain the difference between a gross requirements plan and a net requirements plan.
Question 43
Multiple Choice
Distortion in MRP systems can be minimized when safety stock is held at the:
Question 44
Multiple Choice
Which of the following statements regarding the gross material requirements plan is TRUE?
Question 45
Essay
An order for 110 units of Product A has been made.There are currently 60 units of Product A on hand.Each A requires 2 units of Part B.There are 30 units of B available. (a)Calculate the net requirements for A. (b)Calculate the gross requirements for B. (c)Calculate the net requirements for B.
Question 46
Multiple Choice
Consider the following product structure.
If the demand for product A is 30 units,and there are 10 units of B on hand and none of C,how many units of part D will be needed?
Question 47
Multiple Choice
If safety stock is desired,it should be built into which portion of MRP?
Question 48
True/False
Gross material requirements do not take into account the amount of inventory on hand.
Question 49
Multiple Choice
An order for 50 units of Product A and 60 of B has been placed.There are currently 25 units of Product B on hand.Each A requires 2 units of Part C; each B requires 5 units of C.There are 160 units of C available.What are the net requirements for C?
Question 50
True/False
When safety stock is deemed absolutely necessary,the usual policy is to build it into (increase)the inventory requirement of the MRP logic.
Question 51
Multiple Choice
In MRP,the number of units projected to be available at the beginning of each time period refers to:
Question 52
Multiple Choice
A material requirements plan contains information with regard to all of the following EXCEPT:
Question 53
Essay
________ are the result of adjusting gross requirements for inventory on hand and scheduled receipts.
Question 54
True/False
If 100 units of Q are needed and 10 are already in stock,then the gross requirement is 100 and the net requirement is 90.
Question 55
Multiple Choice
An order for 110 units of Product A has been placed.There are currently 60 units of Product A on hand.Each A requires 4 units of Part B.There are 20 units of B available.What are the net requirements for B?