For an activity-on-node (AON) network,
A) arrows represent activities and nodes represent events.
B) nodes represent activities and arrows indicate precedence relationships.
C) arrows represent events and nodes indicate precedence relationships.
D) nodes indicate precedence relationships and arrows indicates the length of the activity time.
Correct Answer:
Verified
Q50: The key elements of project control include
Q51: Which of the following is not used
Q52: A bar graph displaying when activities are
Q53: In project management the term slack refers
Q54: The longest path through a project network
Q56: _ relationship is the sequential relationship of
Q57: One disadvantage of Gantt charts,especially for large
Q58: Which of the following is not one
Q59: Which of the following is the universal
Q60: _ is the process of making sure
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents