In project management the term slack refers to the amount of time
A) to complete an activity without delaying the project.
B) an activity can be delayed without delaying the project.
C) needed to complete the entire project.
D) required to complete the project's critical activities.
Correct Answer:
Verified
Q48: Project managers must address cultural diversity in
A)project
Q49: Which of the following is one of
Q50: The key elements of project control include
Q51: Which of the following is not used
Q52: A bar graph displaying when activities are
Q54: The longest path through a project network
Q55: For an activity-on-node (AON)network,
A)arrows represent activities and
Q56: _ relationship is the sequential relationship of
Q57: One disadvantage of Gantt charts,especially for large
Q58: Which of the following is not one
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents