The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 81

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the variance for activity E is A) 1.291 weeks B) 1.667 weeks. C) 2.582 weeks. D) 2.778 weeks. Table ZZ
-Using Table ZZ,the variance for activity E is


A) 1.291 weeks
B) 1.667 weeks.
C) 2.582 weeks.
D) 2.778 weeks.

Correct Answer: