The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table ZZ
-Using Table ZZ,the earliest start (ES) time for activity D is
A) 8.17 weeks.
B) 12.67 weeks.
C) 18.33 weeks.
D) 21.67 weeks.
Correct Answer:
Verified
Q80: A project consists of the following activities:
Q81: The following table of probabilistic time estimates
Q82: A project consists of the following four
Q83: Why have projects taken on a more
Q84: What is a scope statement?
Q86: The following table of probabilistic time estimates
Q87: The following table of probabilistic time estimates
Q88: Which of the following statements is generally
Q89: A project consists of the following four
Q90: A project consists of the following four