Figure 15-1 the Following Information Relates to Lancashire Manufacturing: to Produce a Produce
Figure 15-1
The following information relates to Lancashire Manufacturing: To produce a unit of product:
Mixing department 3 minutes per unit
Molding department 5 minutes per unit
Casting department 7 minutes per unit
Finishing department 4 minutes per unit
There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
-Refer to Figure 15-1. How long does it take to produce a batch of 20 units under a traditional manufacturing approach?
A) 380 minutes
B) 415 minutes
C) 35 minutes
D) none of the above
Correct Answer:
Verified
Q45: In a traditional manufacturing setup
A)there is significant
Q49: The order fulfillment value stream focuses on
A)developing
Q50: In a demand-pull system
A)production is triggered by
Q53: The production rate
A) tells how many units
Q55: The value stream
A)is made up of all
Q56: Figure 15-2
The following information relates to Cranmore
Q57: Figure 15-1
The following information relates to Lancashire
Q63: Which of the following is NOT a
Q63: Figure 15 - 3
Based on the following
Q74: Why might labor costs be reduced in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents