A firm is planning to set up an assembly line to assemble 40 units per hour,and 57 minutes per hour are productive.The time to perform each task and the tasks that precede each task are contained in the following table.
(a)Draw a network diagram of precedence relationships.
(b)Compute the required cycle time per unit in minutes.
(c)Compute the theoretical minimum number of workstations required to produce 40 units per hour.
(d)Balance this line using the longest processing time heuristic.
(e)What is the efficiency of the line obtained in part d?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q132: An assembly line consists of 21 tasks
Q137: An assembly line has been designed to
Q140: Develop a solution for the following line
Q141: A facility is trying to set up
Q143: An assembly line with 11 tasks is
Q145: An assembly line is assigned as follows.Station
Q145: Hemo-tech,Inc. ,a biomedical technology and research laboratory,produces
Q308: _ is the maximum time that the
Q311: A company is trying to balance production
Q317: A(n) _ line is a machine-paced product-oriented
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents