Table 16.4
Consider the following MPS,BOM,and inventory data.Blank MRP records are provided at the end of this exam.
Master Production Schedule: The following table shows the MPS start quantities. Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
-Use the information in Table 16.4.Which one of the following statements about item C is BEST?
A) The 100-unit scheduled receipt of 200 units in week 1 can be delayed until week 2 without delaying item D's first planned order release.
B) Its second planned order release is for 200 units in week 6.
C) It has a planned receipt of 180 units in week 5.
D) An order for 60 units should be placed now (in week 1) .
Correct Answer:
Verified
Q68: A technique used for projecting time-phased capacity
Q72: Table 16.4
Consider the following MPS,BOM,and inventory data.Blank
Q73: Table 16.4
Consider the following MPS,BOM,and inventory data.Blank