Table 16.4
Consider the following MPS,BOM,and inventory data.Blank MRP records are provided at the end of this exam.
Master Production Schedule: The following table shows the MPS start quantities. Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
-Use the information in Table 16.4.Which one of the following statements on item C is TRUE?
A) It has a scheduled receipt of 50 units in week 1.
B) Its gross requirement in week 6 is 100 units.
C) Its projected on-hand inventory is 0 units for week 1 through week 6.
D) Its first planned order release is for 100 units in week 4.
Correct Answer:
Verified