Scenario 9.12
Demand = 50,000 units/week
Standard deviation of weekly demand = 15,000 units
Average lead time = 8 weeks
Standard deviation of lead time: 3 weeks
Cycle-service level = 80%
A continuous review system is used to control inventory.
A normal distribution table is appended to this exam.
-Use the information in Scenario 9.12.What is the standard deviation of demand during lead time?
A) greater than 0 but less than or equal to 100,000 units
B) greater than 100,000 units but less than or equal to 200,000 units
C) greater than 200,000 units but less than or equal to 300,000 units
D) greater than 300,000 units
Correct Answer:
Verified
Q14: _ is the planning and controlling of
Q31: A(n) _ occurs when a customer order
Q35: A(n) _ is an order that cannot
Q50: The _ determines the frequency and quantity
Q122: The number of setups (or orders) per
Q150: _ is the cost of preparing a
Q153: Inventory _ cost is the variable cost
Q154: Scenario 9.12
Demand = 50,000 units/week
Standard deviation of
Q158: Scenario 9.12
Demand = 50,000 units/week
Standard deviation of
Q159: Scenario 9.13
Demand = 100,000 units/year
Number of days
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents