Scenario 9.12
Demand = 50,000 units/week
Standard deviation of weekly demand = 15,000 units
Average lead time = 8 weeks
Standard deviation of lead time: 3 weeks
Cycle-service level = 80%
A continuous review system is used to control inventory.
A normal distribution table is appended to this exam.
-Use the information in Scenario 9.12.If the firm decides to increase its cycle-service level to 90%,what is the new reorder point if all other parameters remain the same for this product?
A) greater than 550,000 units
B) greater than 400,000 units but less than or equal to 550,000 units
C) greater than 250,000 units but less than or equal to 400,000 units
D) greater than 150,000 units but less than or equal to 250,000 units
E) greater than 0 but less than or equal to 150,000 units
Correct Answer:
Verified
Q14: _ is the planning and controlling of
Q31: A(n) _ occurs when a customer order
Q35: A(n) _ is an order that cannot
Q50: The _ determines the frequency and quantity
Q149: A _ is an incentive to order
Q150: _ is the cost of preparing a
Q153: Inventory _ cost is the variable cost
Q155: Scenario 9.12
Demand = 50,000 units/week
Standard deviation of
Q158: Scenario 9.12
Demand = 50,000 units/week
Standard deviation of
Q159: Scenario 9.13
Demand = 100,000 units/year
Number of days
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents