Scenario 9.12 Demand = 50,000 Units/week

Question 154

Multiple Choice

Scenario 9.12
Demand = 50,000 units/week
Standard deviation of weekly demand = 15,000 units
Average lead time = 8 weeks
Standard deviation of lead time: 3 weeks
Cycle-service level = 80%
A continuous review system is used to control inventory.
A normal distribution table is appended to this exam.
-Use the information in Scenario 9.12.If the firm decides to increase its cycle-service level to 90%,what is the new reorder point if all other parameters remain the same for this product?


A) greater than 550,000 units
B) greater than 400,000 units but less than or equal to 550,000 units
C) greater than 250,000 units but less than or equal to 400,000 units
D) greater than 150,000 units but less than or equal to 250,000 units
E) greater than 0 but less than or equal to 150,000 units

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents