![Two contract labor companies are competing for work being outsourced by Febrero SpA. One contractor, Terza, has a learning rate governed by a tripling of output at a 90% rate and the other contractor, Segundo, has a learning rate governed by the conventional doubling of output at a 90% rate. Both Terza and Segundo take 20 minutes to complete the first unit they are given for bid estimation purposes. How many more units must Terza make than Segundo before their time per unit drops below 15 minutes? [Note: a calculator is required to answer this question.]](https://scanned-questions.quizplus.com/1057595.webp)
Two contract labor companies are competing for work being outsourced by Febrero SpA. One contractor, Terza, has a learning rate governed by a tripling of output at a 90% rate and the other contractor, Segundo, has a learning rate governed by the conventional doubling of output at a 90% rate. Both Terza and Segundo take 20 minutes to complete the first unit they are given for bid estimation purposes. How many more units must Terza make than Segundo before their time per unit drops below 15 minutes? [Note: a calculator is required to answer this question.]
Correct Answer:
Verified
15 = 20 × n ˡᵒᵍ⁽.⁹⁰⁾/ˡᵒᵍ⁽²⁾
ⁿ ˡ...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q23: The fifth unit took 36.3406 hours to
Q24: A contractor is preparing a bid to
Q25: It took 100 hours to produce the
Q26: A company is introducing a new product.
Q27: The estimated time to produce the first
Q29: Case I.1
The production schedule for a new
Q30: The learning rate depends on factors such
Q31: Tim usually exhibits a 90% learning rate
Q32: In Troix City, the learning rate is
Q33: Given that the fifth unit took 10
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents