A company could add $10,000 per week in revenues if the project depicted in Table 7.10 could be shortened. Table 7.10 Four possible options exist to crash activities: crash A by one week at a cost of $6,000;crash C by two weeks at a cost of $15,000;crash E by one week at a cost of $2,000;and crash I one week at a cost of $7,000.What is the maximum amount of additional profit that can be made by crashing an option (or options) ?
A) less than or equal to $4,000
B) greater than $4000 but less than or equal to $8,000
C) greater than $8000 but less than or equal to $12,000
D) greater than $12,000
Correct Answer:
Verified
Q84: The optimistic time is the probable time
Q90: Risk is a measure of the probability
Q91: A risk-management plan contains all identified risks
Q97: If a project has exactly one critical
Q97: Table 7.9 Q98: You are given the following information about Q108: To calculate the probability of completing a Q110: Table 7.13 Q116: Table 7.2 Q117: Information accuracy relative to the completeness of
All activity times for the project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents