If a project has exactly one critical path,which of the following statements is TRUE?
A) Crashing an activity on the critical path will always result in an increase in total project profits.
B) Activities on the critical path cannot be crashed.
C) Crashing an activity on the critical path will always result in a reduced total project completion time.
D) The best schedule is one in which all activities are crashed as much as possible.
Correct Answer:
Verified
Q83: A project is currently scheduled to be
Q84: The optimistic time is the probable time
Q90: Risk is a measure of the probability
Q91: A risk-management plan contains all identified risks
Q92: You are given the following information about
Q97: Table 7.9 Q98: You are given the following information about Q99: A company could add $10,000 per week Q108: To calculate the probability of completing a Q116: Table 7.2
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents