Which of the following statements is true about the MRP plan when using lot-for-lot ordering?
A) The quantity of gross requirements for a child item is always equal to the quantity of planned order releases for its parent.
B) The quantity of gross requirements for a child item is equal to the quantity of planned order release(s) multiplied by the number of child items used in the parent assembly.
C) The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent.
D) The quantity and gross requirements for a child item is always equal to the quantity of net requirements for its parent.
E) The quantity of gross requirements for a parent item is equal to the sum of net requirements for all child items.
Correct Answer:
Verified
Q65: When safety stock is deemed absolutely necessary,
Q70: Linking a part requirement with the parent
Q73: The MPS calls for 50 units of
Q78: If safety stock is desired it should
Q81: Which of the following is a step
Q82: An item's holding cost is 60 cents
Q83: One of the tools that is particularly
Q84: Distribution resource planning (DRP) is
A) a transportation
Q94: For the lot-sizing technique known as lot-for-lot
Q98: A firm makes numerous models of mowers,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents