Network Logic Suggests That

Question 28

Multiple Choice

Network logic suggests that: Network logic suggests that:   A)  Activity D can start any time. B)  Activity A must be complete before Activity B can be done. C)  Activities A, B and C must be complete before Activity D can be done. D)  Activity C must begin before Activity B begins.


A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A, B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.

Correct Answer: