What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?
A) 14
B) 13
C) 12
D) 11
Correct Answer:
Verified
Q42: An activity has a pessimistic time that
Q45: Use the information in the table to
Q46: Use the information in the table to
Q48: Use the information in the table to
Q50: What is the early start time for
Q51: What is the slack time for activity
Q53: Use the network diagram and activity lengths
Q54: What is the early finish time for
Q57: An activity has an optimistic time estimate
Q58: Activity Z has estimates a = 5,b
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents