Use the information in the table to determine the late finish time for Activity B.
A) day 17
B) day 26
C) day 20
D) day 23
Correct Answer:
Verified
Q42: An activity has a pessimistic time that
Q43: What is the late start time for
Q45: Use the information in the table to
Q46: Use the information in the table to
Q49: What is the late finish time for
Q50: What is the early start time for
Q51: What is the slack time for activity
Q53: Use the network diagram and activity lengths
Q57: An activity has an optimistic time estimate
Q58: Activity Z has estimates a = 5,b
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents