Solved

Which of the Following Items Best Describe the Process Steps

Question 37

Multiple Choice

Which of the following items best describe the process steps to construct a Work Breakdown Structure (WBS) ?


A) identify major deliverables - divide into smaller deliverables - continue until right size - review
B) identify smallest deliverables - assemble into larger deliverables - continue until right size - review
C) identify project goals - decompose into objectives - develop metrics - document results
D) identify WBS components - identify WBS elements - identify work packages - develop WBS dictionary

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents