Question 21
Multiple Choice
The work package provides the basis for future project planning activities including all of the following EXCEPT:
Question 22
Multiple Choice
The project scope planning processes include all of the following EXCEPT:
Question 23
Multiple Choice
Which of the following statements is true concerning the adoption of rolling wave planning in project management?
Question 24
Multiple Choice
Work Breakdown Structures typically include one or more intermediate levels. Which of the following statements correctly describe the nature of these intermediate levels?
Question 25
Multiple Choice
The Work Breakdown Structure (WBS) is a framework that will be used as a basis for further planning activities including all the following EXCEPT:
Question 26
Multiple Choice
Which of the following items best describes a project Work Breakdown Structure (WBS) ?
Question 27
Multiple Choice
Which of the following statements concerning work packages is NOT correct?
Question 28
True/False
Each potential change to a project is normally documented by some sort of change request.
Question 29
Multiple Choice
For each component in the Work Breakdown Structure (WBS) ,the WBS dictionary includes:
Question 30
Multiple Choice
All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS) for a project EXCEPT:
Question 31
Multiple Choice
All of the following conventions are widely adopted when project teams create the second level of the project Work Breakdown Structure (WBS) EXCEPT:
Question 32
Multiple Choice
Define Scope is the process of developing:
Question 33
Multiple Choice
Work Breakdown Structures can be displayed in a variety of formats including which of the following?
Question 34
Multiple Choice
For each component in the Work Breakdown Structure (WBS) ,the WBS dictionary includes all the following fields that will be progressively elaborated EXCEPT:
Question 35
Multiple Choice
Formally documented procedures that define how project deliverables and documentation will be controlled,changed and approved are collectively known by which of the following terms?