Solved

For Each Component in the Work Breakdown Structure (WBS),the WBS

Question 34

Multiple Choice

For each component in the Work Breakdown Structure (WBS) ,the WBS dictionary includes all the following fields that will be progressively elaborated EXCEPT:


A) a brief scope description
B) name of team member(s) that will be responsible for creating the deliverables
C) a list of associated activities
D) defined deliverables

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents