Multiple Choice
Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods represent a potentially viable strategy to reduce work overloads EXCEPT:
A) Require all project resources to work overtime
B) Split an activity into two activities and delay the second part.
C) Re-sequence activities when logically feasible.
D) Reassign certain activities to other workers.
Correct Answer:
Verified