Contemporary Project Management
Quiz 8: Resourcing Projects
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 21
Multiple Choice
Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4. Which activity should you crash to reduce this project by one day with the least incremental cost?
Question 22
Multiple Choice
Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3. Which activity is an ideal candidate to delay in order to achieve a feasible schedule?
Question 23
Multiple Choice
Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods represent a potentially viable strategy to reduce work overloads EXCEPT:
Question 24
Multiple Choice
Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3. If only six programmers are available to support this project,which of the following conclusions is valid?
Question 25
Multiple Choice
Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1. What responsibility should the contract officer assume with respect to the statement of work?
Question 26
True/False
RACI (Responsible,Approve,Consult,Inform)charts go beyond a communication plan in that they identify every project activity and specify the exact involvement of each stakeholder.
Question 27
Multiple Choice
Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4. What is the cost to complete this project in the normal time?
Question 28
Multiple Choice
Project managers must often face the challenge of compressing the project schedule. All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
Question 29
Multiple Choice
The components (principles) of Critical Chain Project Management include which of the following?
Question 30
Multiple Choice
A common tool project teams use is a responsibility assignment matrix (RAM) . Typically,this chart will depict:
Question 31
Multiple Choice
Figure 8-2 Software Programmer Loading Chart -Consider the software programmer loading chart presented in Figure 8-2. What percent of available time is the software programmer assigned to work activities on Thursday?
Question 32
Multiple Choice
Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4. What is the incremental cost to achieve a one-day reduction in the duration of this project in the most cost efficient manner?
Question 33
Multiple Choice
When estimating resource needs,project teams should consider all the following EXCEPT:
Question 34
Multiple Choice
Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3. How many programmers are required during the fifth week of this project?
Question 35
Multiple Choice
Critical Chain Project Management (CCPM) was developed to address several problems that are common in organizations that use traditional project scheduling. Which of the following describes a common problem addressed by CCPM?