Change control includes which of the following activities?


A) identifying, documenting, approving or rejecting, and controlling changes to project baselines
B) brainstorming, selecting and implementing new ideas
C) recruiting, selecting and training new team members
D) identifying and implementing changes to the project charter

Correct Answer: