Question 41
Multiple Choice
Five samples of size 3 were collected for a variable measurement.All sample data were greater than or equal to 4.0.The sample means and sample ranges are provided in the following table.
The values of which sample are identical?
Question 42
Multiple Choice
A p-chart is also called a:
Question 43
Multiple Choice
Which of the following is NOT an indication of an out-of-control process?
Question 44
Multiple Choice
A delivery company defines a "defect" as a package delivered later than the promised delivery time.Management wants to monitor the proportion of packages per week delivered beyond their promised delivery time.Management plans to sample 150 packages per week.The appropriate control chart is a(n) :
Question 45
Multiple Choice
A manager at a canning company wants to monitor the number of orange juice cans it produces each day that are beyond the upper specification limit for can diameter.Each day an employee will randomly select 150 cans and then determine and plot the number of cans that are beyond the upper specification limit for can diameter.The appropriate control chart is a(n) :
Question 46
Multiple Choice
The s-chart is recommended when:
Question 47
Multiple Choice
If the process mean and variance do not change over time,the process is considered to be:
Question 48
Multiple Choice
A precision parts manufacturer produces bolts for use in military aircraft. The specifications for bolt length are
37.50
±
0.25
Â
c
m
37.50 \pm 0.25 \mathrm{~cm}
37.50
±
0.25
Â
cm
. The company has established an
x
ˉ
\bar{x}
x
ˉ
-chart and an
R
R
R
-chart using samples of size five. The centerlines for the
x
ˉ
\bar{x}
x
ˉ
chart and
R
R
R
-chart are set at
37.65
Â
c
m
37.65 \mathrm{~cm}
37.65
Â
cm
and
1.03
Â
c
m
1.03 \mathrm{~cm}
1.03
Â
cm
, respectively. What is the value of
C
p
k
C_{p k}
C
p
k
​
for this process?
Question 49
Multiple Choice
Which of the following is a likely cause of the control chart pattern known as a "trend?"
Question 50
Multiple Choice
Determine the sample standard deviation for the following sample data: 7,9,2,0,1,and 5.
Question 51
Multiple Choice
A precision parts manufacturer produces bolts for use in military aircraft. The specifications for bolt length are
37.50
±
0.25
Â
c
m
37.50 \pm 0.25 \mathrm{~cm}
37.50
±
0.25
Â
cm
. The company has established an
x
ˉ
\bar{x}
x
ˉ
-chart and an
R
R
R
-chart using samples of size five. The centerlines for the
x
ˉ
\bar{x}
x
ˉ
chart and
R
R
R
-chart are set at
37.65
Â
c
m
37.65 \mathrm{~cm}
37.65
Â
cm
and
1.03
Â
c
m
1.03 \mathrm{~cm}
1.03
Â
cm
, respectively. What is the value of
C
p
C_{p}
C
p
​
for this process?
Question 52
Multiple Choice
Six samples of size 10 were collected.The data are provided in the following table.
The upper control limit (UCL) and lower control limit (LCL) for an s-chart are:
Question 53
Multiple Choice
For variables data,the sample means are assumed to be:
Question 54
Multiple Choice
A company wishes to monitor the variation in the length of time it takes to process and send a bill to a customer.Five bills will be randomly selected each day and the length of time it takes to process and send the bill to a customer will be recorded for each bill.The appropriate control chart is a(n) :
Question 55
Multiple Choice
The output of a process is stable and normally distributed.If the process mean equals 23.5,the percentage of output expected to be less than or equal to the mean:
Question 56
Multiple Choice
Short repeated patterns in a control chart,with alternating high peaks and low valleys,are known as:
Question 57
Multiple Choice
Which of the following pairs of charts are used together?
Question 58
Multiple Choice
If a process is neither capable nor in control,the appropriate first step is to:
Question 59
Multiple Choice
Each day,a manufacturing company producing circuit boards will randomly sample 60 circuit boards and then determine and plot the number of defects contained in each of these boards.The appropriate control chart is a: