Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
Project Management Achieving Competitive Advantage
Quiz 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 41
True/False
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Question 42
True/False
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Question 43
Essay
What is the underlying theory to the three time estimates approach? What data distribution should be applied in this case and what confidence should a project manager place in the calculations associated with this technique?
Question 44
True/False
You must know the mean of an activity in order to determine its standard deviation.
Question 45
True/False
The late start time should be calculated using a forward pass through the network.
Question 46
Multiple Choice
What is the early start time for Activity G given the activity times and precedence requirements shown in the table?
Question 47
Essay
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
Question 48
Multiple Choice
What is the early start time for Activity D given the activity times and precedence requirements shown in the table?
Question 49
Multiple Choice
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?
Question 50
True/False
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.