Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Business
Study Set
Project Management Achieving Competitive Advantage
Quiz 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 21
True/False
A merge activity has two or more immediate predecessors.
Question 22
Multiple Choice
Prior to creating a network, it is important to:
Question 23
Multiple Choice
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
Question 24
Multiple Choice
An activity has an optimistic time estimate of 17 days, a most likely estimate of 23 days, and a pessimistic estimate of 37 days. What is the variance of the activity?
Question 25
True/False
At a merge point in a forward pass, the largest preceding early finish becomes the early start for that node.
Question 26
Essay
Consider a project composed of activities X and Y having equal length and performed in that order. Both activities can be laddered such that the first half of each activity is the predecessor for its own second half, so X1 precedes X2 and Y1 precedes Y2. The first half of X1 is also the predecessor for Y1. If the laddering procedure were performed again activities X and Y would be divided in four parts each, with precedence working as it did in the first split. Derive an expression for the minimum length of the project as laddering increases.
Question 27
Multiple Choice
An activity has an optimistic time estimate of 12 days, a most likely estimate of 16 days, and a pessimistic estimate of 22 days. What is the expected standard deviation of the activity?
Question 28
Multiple Choice
Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity) . Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the expected completion time of the laddered project?
Question 29
Multiple Choice
Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity) . Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the expected completion time of the laddered project?
Question 30
Essay
What does a network diagram illustrate and why are they important in project management?
Question 31
True/False
Burst activities are those with two or more successor activities.
Question 32
Multiple Choice
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?
Question 33
Multiple Choice
Ray's shipment of materials hit every red light and traffic jam on the way to the site. Upon arrival, half of the material was judged defective, necessitating a trip back to the supplier, and then the same arduous journey back to the site once the new materials were loaded. Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip. In the final analysis:
Question 34
Multiple Choice
The variance of an activity is given by:
Question 35
Multiple Choice
Activity Z has estimates a = 5, b = 12, m = 7; activity X has estimates a = 5, b = 11, m = 6; and activity Y has estimates a = 3, b = 11, m = 8. Which of the following statements is BEST?
Question 36
Multiple Choice
An activity has an optimistic time estimate of 25 days, a most likely estimate of 29 days, and a pessimistic estimate of 34 days. What is the expected duration of the activity?